Description


Page : 141

Sondrestrom Lidar Operation Log


Operator(s) : E.Gudmundsson
Purpose : Routine data collection co radar
Date(s) : 980821 - 980822
File(s) : L9808210 - L9898210
Comments :
Logfile : l9808210.log

Setup:0


Page : 142
[Variables]
Dye Power=66mJ
Rayleigh Power=580mJ

[0]
90% PMT Iris=not_installed
Rayleigh System=On
Dye System=On
Daystar=In
Polerizer=Out
HalfWave Plates=Tracking
Filter Wheel=3:Open

[1]
90% PMT Iris=not_installed
Rayleigh System=On
Dye System=On
Daystar=Out
Polerizer=Out
HalfWave Plates=Tracking
Filter Wheel=2:532(.5nm)

Logsheet:0


Page : 143

Sondrestrom Lidar Operation Log


Log Sheet 1 of 1
Operators : E.Gudmundsson
Date(s) : 980821 - 980822
File(s) : L9808210 - L9898213
FilesTime [UT]CommentsCntSOpe
L980821021:13:23Start of experiment00EG
L989821021:14:27some cirrus up there but we're running anyway8140EG
L980821023:24:43Rayleigh HG adjusted3240EG
L980821023:24:53Clouds getting worse3240EG
L980821100:27:19Rayleigh HG adjusted0EG
L980821101:00:55Ups!! Because of intence discussions with SRI employes0EG
I forgot to change the setup
L980821101:02:13jumping to setup 12930EG
L980821101:04:19resuming with setup 11EG
L980821101:05:27UPS !!The polarizer was not in the system when i changed3301EG
corrected setup 0 ( was changed to indicate actual used setup)
L980821102:15:12Rayleigh Convergence mirror adjusted12961EG
L980821203:14:19Wavemeter still on track at 589.158nm19911EG
L980821305:09:01Ups last record ruined10151EG
L980821305:09:09End of experiment1EG